Mechanic's lien deadlines in Utah: the 2026 guide for subcontractors

If you furnish labor or materials on a Utah project and you don't get paid, a mechanic's lien is how you force the issue. But the right to file expires fast. Here are the deadlines that matter, in plain language.

  1. Preliminary / Pre-Lien Notice

    Many Utah projects require a subcontractor or supplier to serve a preliminary or pre-lien notice early in the job, generally within about 20 days of first furnishing labor or materials, to keep lien rights alive.

    Utah Code § 38-1a-101 et seq.

  2. Record Your Mechanics Lien

    Record your mechanics lien with the county recorder, generally within about 90 days after the last day you furnished labor or materials to the project.

    Utah Code § 38-1a-101 et seq.

  3. Deadline to Enforce the Lien (Lawsuit)

    File a lawsuit to enforce (foreclose) your lien, generally within about 6 months after the lien is recorded, or the lien can expire.

    Utah Code § 38-1a-101 et seq.

See your exact Utah dates

Enter your job dates in the free calculator, or let LienAlert track every deadline for every job and remind you before each one.

This guide is general information based on public Utahstatutes, not legal advice, and your exact deadlines depend on your facts. Always confirm with a licensed Utah attorney before relying on a date.