Mechanic's lien deadlines in Oregon: the 2026 guide for subcontractors
If you furnish labor or materials on a Oregon project and you don't get paid, a mechanic's lien is how you force the issue. But the right to file expires fast. Here are the deadlines that matter, in plain language.
The deadlines, step by step
Preliminary / Pre-Lien Notice
Many Oregon projects require a subcontractor or supplier to serve a preliminary or pre-lien notice early in the job, generally within about 8 days of first furnishing labor or materials, to keep lien rights alive.
Or. Rev. Stat. § 87.001 et seq.
Record Your Mechanics Lien
Record your mechanics lien with the county recorder, generally within about 75 days after the last day you furnished labor or materials to the project.
Or. Rev. Stat. § 87.001 et seq.
Deadline to Enforce the Lien (Lawsuit)
File a lawsuit to enforce (foreclose) your lien, generally within about 4 months after the lien is recorded, or the lien can expire.
Or. Rev. Stat. § 87.001 et seq.
Good to know
- General Oregon mechanics lien deadlines compiled from public statutes (Or. Rev. Stat. § 87.001 et seq.).
- These dates are approximate and depend on your role, the property type, and any notices the owner files. Many states also require an earlier preliminary or pre-lien notice, so confirm your state's notice rules.
- When a deadline falls on a weekend or legal holiday it is generally treated as extended to the next business day.
- This is general information, not legal advice. Confirm every deadline for your specific situation before you rely on it.
See your exact Oregon dates
Enter your job dates in the free calculator, or let LienAlert track every deadline for every job and remind you before each one.
This guide is general information based on public Oregonstatutes, not legal advice, and your exact deadlines depend on your facts. Always confirm with a licensed Oregon attorney before relying on a date.