Mechanic's lien deadlines in Minnesota: the 2026 guide for subcontractors

If you furnish labor or materials on a Minnesota project and you don't get paid, a mechanic's lien is how you force the issue. But the right to file expires fast. Here are the deadlines that matter, in plain language.

  1. Preliminary / Pre-Lien Notice

    Many Minnesota projects require a subcontractor or supplier to serve a preliminary or pre-lien notice early in the job, generally within about 45 days of first furnishing labor or materials, to keep lien rights alive.

    Minn. Stat. § 514.01 et seq.

  2. Record Your Mechanics Lien

    Record your mechanics lien with the county recorder, generally within about 120 days after the last day you furnished labor or materials to the project.

    Minn. Stat. § 514.01 et seq.

  3. Deadline to Enforce the Lien (Lawsuit)

    File a lawsuit to enforce (foreclose) your lien, generally within about 12 months after the lien is recorded, or the lien can expire.

    Minn. Stat. § 514.01 et seq.

See your exact Minnesota dates

Enter your job dates in the free calculator, or let LienAlert track every deadline for every job and remind you before each one.

This guide is general information based on public Minnesotastatutes, not legal advice, and your exact deadlines depend on your facts. Always confirm with a licensed Minnesota attorney before relying on a date.