Mechanic's lien deadlines in California: the 2026 guide for subcontractors
If you furnish labor or materials on a California project and you don't get paid, a mechanic's lien is how you force the issue. But the right to file expires fast. Here are the deadlines that matter, in plain language.
The deadlines, step by step
Serve Preliminary (20-day) Notice
Most subcontractors and suppliers must serve a Preliminary Notice on the owner, direct contractor, and lender within 20 days of first furnishing labor or materials. Serving late limits your claim to amounts furnished in the 20 days before notice and afterward.
Cal. Civ. Code §§ 8200, 8204
Record Mechanics Lien
Record the mechanics lien within 90 days after the work of improvement is completed, unless the owner records a Notice of Completion or Cessation, which shortens this to 30 days for subcontractors (60 days for the direct contractor). The date shown uses your last furnishing date.
Cal. Civ. Code §§ 8412, 8414
File Action to Foreclose
File a lawsuit to foreclose the mechanics lien within 90 days after the lien is recorded, or the lien expires.
Cal. Civ. Code § 8460
Good to know
- Based on the California mechanics lien statutes (Cal. Civ. Code §§ 8000 et seq.).
- If the owner records a Notice of Completion or Cessation, the lien recording window is shortened (generally to 30 days for subcontractors). Confirm whether one was recorded.
- When a deadline falls on a weekend or legal holiday it is generally treated as extended to the next business day.
- This is general information, not legal advice. Confirm every deadline with a licensed California attorney before relying on it.
See your exact California dates
Enter your job dates in the free calculator, or let LienAlert track every deadline for every job and remind you before each one.
This guide is general information based on public Californiastatutes, not legal advice, and your exact deadlines depend on your facts. Always confirm with a licensed California attorney before relying on a date.